Additional projects scheduled for this summer include:

  • Replacement of the back doors at the Stoller Center, before July 1
  • Installation of sound panels in Warner Hall, Room 5, before July 1
  • Lighting at Berglund, Murdock and Gilbert halls, June 4
  • Refreshing bathrooms in McCormick Hall suites, June 17 to 27
  • Remodel of 10 rooms on third floor of Clark Hall, all summer
  • Lighting in McCormick Hall lobby, June 17 to 28
  • Resurfacing of track at Hanson Stadium, June 24 to July 20
  • Refreshing of McCormick Hall laundry room, June 24 — June 27
  • Reflooring of Walter Hall kitchen, July 22 to 26
  • Lock changeovers at Vandervelden Apartments, all summer
  • Sealing of Price Hall windows, Aug. 12 to 23

 